Adjudicator’s frolics - Victory House General Partner Limited v RGB P&C Limited
The Technology and Construction Court handed down another decision on natural justice in adjudications in January that will come as some relief to adjudicators.


The Technology and Construction Court handed down another decision on natural justice in adjudications in January that will come as some relief to adjudicators.
Basically, the original contract was to build a hotel, part of which required a transformer. After some delays, the parties entered into a Memorandum Of Understanding (MOU) such that the transformer could be installed and payments made.
RGB P&C Limited’s (RGB) main argument was that the contract was binding and Victory House General Partner Limited’s (VH) main argument was that the MOU was binding. So which was the adjudicator to choose?
The adjudicator instead decided that “the true effect of the MOU was to suspend the obligation on VH to make interim payments under the contract until such time as the transformer was installed and operational”. Of course, no-one had actually made that argument before the adjudicator. That was a new solution to the problem.
VH argued that this was a breach of natural justice. VH said that the adjudicator had gone off on a “frolic of his own”.
The judge disagreed, giving the following reasons (summarised):
- The parties were both aware that a central question was the interpretation of the MOU;
- The adjudicator had asked questions on the point during the adjudication;
- RGB clearly responded to the adjudicator’s questions;
- VH responded to the adjudicator’s questions indirectly;
- VH had the opportunity to respond to the adjudicator’s question directly;
- The rule in Cantillon v Urvasco [2008] is that if a party has argued a point and the other does not come back on that point, it does not cause a breach of natural justice. In this case, the adjudicator had asked questions about exactly this point.
The adjudicator’s decision was therefore upheld.This decision follows a relatively long line of cases from Balfour Beatty Construction v Lambeth [2002], where the court found that the adjudicator’s reliance on his own critical path analysis was in breach of natural justice, to AECOM Design Build v Staptina Engineering Services [2017], where the court has found that an adjudicator is entitled to make a finding that neither party submitted, so long as the parties were sufficiently able to canvass their views on the point.


Charity of the Month: Sue Lambert Trust
Leathes Prior is delighted to be supporting the Sue Lambert Trust as our Charity of the Month for February 2026. Sue Lambert Trust is a leading charity in Norfolk offering free therapeutic counselling and support services to survivors of sexual violence and abuse.



Supreme Court ruling set to impact NHS - Children injured by NHS can claim damages for lifetime lost earnings
In February 2026, the Supreme Court passed a ruling which is set to significantly increase the amount of damages the NHS may have to pay for claims brought in respect of children injured at birth, as a result of medical negligence.

.jpg)

The Value of Planning Ahead: LPAs & Court of Protection
Putting LPAs in place allows you to choose trusted people to make decisions for you if you lose capacity in the future. This avoids the need for loved ones to make a costly and time-consuming deputyship application to the Court of Protection. With more people likely to experience conditions affecting capacity, more families may need to turn to the Court for support where no LPAs are in place.



















.jpg)













