Adjudicator’s frolics - Victory House General Partner Limited v RGB P&C Limited
The Technology and Construction Court handed down another decision on natural justice in adjudications in January that will come as some relief to adjudicators.


The Technology and Construction Court handed down another decision on natural justice in adjudications in January that will come as some relief to adjudicators.
Basically, the original contract was to build a hotel, part of which required a transformer. After some delays, the parties entered into a Memorandum Of Understanding (MOU) such that the transformer could be installed and payments made.
RGB P&C Limited’s (RGB) main argument was that the contract was binding and Victory House General Partner Limited’s (VH) main argument was that the MOU was binding. So which was the adjudicator to choose?
The adjudicator instead decided that “the true effect of the MOU was to suspend the obligation on VH to make interim payments under the contract until such time as the transformer was installed and operational”. Of course, no-one had actually made that argument before the adjudicator. That was a new solution to the problem.
VH argued that this was a breach of natural justice. VH said that the adjudicator had gone off on a “frolic of his own”.
The judge disagreed, giving the following reasons (summarised):
- The parties were both aware that a central question was the interpretation of the MOU;
- The adjudicator had asked questions on the point during the adjudication;
- RGB clearly responded to the adjudicator’s questions;
- VH responded to the adjudicator’s questions indirectly;
- VH had the opportunity to respond to the adjudicator’s question directly;
- The rule in Cantillon v Urvasco [2008] is that if a party has argued a point and the other does not come back on that point, it does not cause a breach of natural justice. In this case, the adjudicator had asked questions about exactly this point.
The adjudicator’s decision was therefore upheld.This decision follows a relatively long line of cases from Balfour Beatty Construction v Lambeth [2002], where the court found that the adjudicator’s reliance on his own critical path analysis was in breach of natural justice, to AECOM Design Build v Staptina Engineering Services [2017], where the court has found that an adjudicator is entitled to make a finding that neither party submitted, so long as the parties were sufficiently able to canvass their views on the point.

Autumn Budget 2025: Agricultural Property Relief & Business Property Relief Changes
It was announced in the 2025 Budget that from 6 April 2026, changes will be made to agricultural property relief and business property relief. These changes bring APR and BPR in line with the nil-rate band rules, meaning unused allowances can be transferred to a surviving spouse or civil partner. This is a significant step towards making estate planning easier for families who own farms or businesses.



The Employment Rights Act 2025 is expected to come into force tomorrow (18 December 2025)
After an extended period of back-and-forth amendments between Parliament and the House of Lords, on 16 December 2025, the ERB finally received approval from the House of Lords, with the formality of Royal Assent due to take place tomorrow (18 December 2025). Head of LP Employment, Dan Chapman, explains...

































